Storage Period
5 storage months (11.11.2026 - 31.03.2027)
Working Gas Volume
39.313.342 kWh
Max. Injection Output
573.097 kWh/day
Max. Withdrawal Output
711.572 kWh/day
Max. filling time of 90 % of capacity
9 February 2027 (90 days)
There was a planned shutdown at Uhřice USF between 11 September and 24 September 2022.
During the shutdown, a record 16 reinforcements were replaced at Uhřice USF and at MS Brumovice.
At the same time, new safety reinforcements were installed at the USF probe collector, improving operating safety and reliability (see the photo)
All the planned servicing and repair work was completed on time, and the equipment is ready to meet the requirements of our customers.