CURRENT INFORMATION
Date | Total available withdrawal capacity (MWh/day) | Total available injection capacity (MWh/day) |
---|---|---|
31.5.2023 | 75 804 | 53 327 |
30.5.2023 | 75 804 | 53 448 |
29.5.2023 | 75 804 | 53 327 |
28.5.2023 | 75 804 | 53 327 |
27.5.2023 | 75 804 | 53 327 |
26.5.2023 | 60 700 | 53 327 |
25.5.2023 | 60 700 | 53 437 |
24.5.2023 | 60 700 | 53 349 |
Date | Total contractual withdrawal capacity (MWh/day) | Total contractual injection capacity (MWh/day) |
---|---|---|
31.5.2023 | 75 804 | 53 327 |
30.5.2023 | 75 804 | 53 448 |
29.5.2023 | 75 804 | 53 327 |
28.5.2023 | 75 804 | 53 327 |
27.5.2023 | 75 804 | 53 327 |
26.5.2023 | 60 700 | 53 327 |
25.5.2023 | 60 700 | 53 437 |
24.5.2023 | 60 700 | 53 349 |
Date | Withdrawals (MWh/day) | Injections (MWh/day) | Price |
---|---|---|---|
31.5.2023 | 0 | 0 | 0 |
30.5.2023 | 0 | 0 | 0 |
29.5.2023 | 0 | 0 | 0 |
28.5.2023 | 0 | 0 | 0 |
27.5.2023 | 0 | 0 | 0 |
26.5.2023 | 0 | 0 | 0 |
25.5.2023 | 0 | 0 | 0 |
24.5.2023 | 0 | 0 | 0 |
Date | Withdrawals (MWh/day) | Injections (MWh/day) |
---|---|---|
31.5.2023 | 0 | 0 |
30.5.2023 | 0 | 0 |
29.5.2023 | 0 | 0 |
28.5.2023 | 0 | 0 |
27.5.2023 | 0 | 0 |
26.5.2023 | 0 | 0 |
25.5.2023 | 0 | 0 |
24.5.2023 | 0 | 0 |
Date | Current capacity in MWh | Withdrawals (MWh/day) | Injections (MWh/day) |
---|---|---|---|
31.5.2023 | 2 117 276 | 112 | 43 353 |
Year | Total technical capacity (GWh) | Contracted capacity (GWh) | Free capacity (GWh) |
---|---|---|---|
2022/23 | 3 420 | 3 420 | 0 |
2023/24 | 3 493 | 3 493 | 0 |
2024/25 | 3 530 | 2 600 | 930 |
Storage Year | Working Gas Volume [GWh] | Max. contractual withdrawals [GWh/day] | Max. contractual injections [GWh/day] |
---|---|---|---|
2028 | 3 650 | 96 | 59 |
2027 | 3 650 | 96 | 59 |
2026 | 3 650 | 96 | 59 |
2025 | 3 610 | 96 | 59 |
2024 | 3 570 | 96 | 59 |
2023 | 3 493 | 96 | 59 |
2022 | 3 420 | 96 | 59 |
2021 | 3 420 | 107 | 59 |
2020 | 3 420 | 115 | 64 |
Shutdown date | Reduction in daily storage during the shutdown in % | Type of shutdown | Note | |
---|---|---|---|---|
Daily injections | Daily withdrawals | |||
11.9. 06:00 - 25.9. 06:00 2023 | 100% | 100% | planned | Maintenance |
12. 9. – 25. 9. 2022 | 100% | 100% | planned | Regular maintenance at UGS Uhřice |
13.9 - 26.9.2021 | 100% | 100% | planned | Regular maintenance at UGS Uhřice |
30. - 31.8.2021 | 100% | 100% | planned | Maintenance at MS Brumovice – testing of alarm/shutdown sequences |
14. – 22. 9. 2020 | 100% | 100% | planned | Limitation caused by TSO (Net4Gas), repair works of pipeline DN 700 RU Mutěnice – TU Diváky |
14.9. – 27.9.2020 | 100% | 100% | planned | Regular maintenance at UGS Uhřice |
3.6. – 16.6.2019 | 100% | 100% | planned | Regular maintenance at UGS Uhřice |
30.10.2018, 1.11.2018 | 50% | 50% | planned | Limitation caused by N4G (cleaning of pipeline DN 700 RU Mutěnice – PRS V.Němčice) |
13.9.2018, 20.9.2018 | 17% | 17% | planned | Limitation caused by N4G (cleaning of pipeline DN 700 RU Mutěnice – PRS V.Němčice) |
10.9.2018 – 23.9.2018 | 100% | 100% | planned | Regular maintenance at UGS Uhřice |
30.10.2017 – 12.11.2017 | 100% | 100% | planned | Maintenance at MS Brumovice |